CIL Installment Policy

Community Infrastructure Levy (CIL)

Payment by Instalments Policy

This policy has been prepared in accordance with Regulation 69B of the Community Infrastructure Levy (Amendment) Regulations 2011. 

The Council will allow payment of CIL by instalments according to the total amount [1] of the liability as follows:

Amount of CIL Liability

Number of Instalments

Payment Periods and Amounts

Any amount less than £100,000

No instalments

Total amount payable within 60 days of commencement of development.

Amounts from £100,000 to £250,000

Two instalments

£100,000 payable within 60 days of commencement of development.

Balance payable within 120 days of commencement of development.

Amounts from £250,000 to £500,000

Three instalments

£100,000 payable within 60 days of commencement of development.

Balance payable in a further two instalments of equal amount within 120 and 180 days of commencement of development.

Any amount greater than £500,000

Four instalments

£250,000 payable within 60 days of commencement of development.

Balance payable in a further three instalments of equal amount within 120, 180 and 240 days of commencement of development.

Date of Effect: This policy came into effect on 1 January 2012.

[1] Note: The total amount of CIL is the amount shown on the Liability Notice and may include components for London Borough of Redbridge and the Mayor of London.