Redbridge Council has issued an update on the Wanstead Leisure Centre and school redevelopment project following confirmation that the main contractor, Jerram Falkus, has entered administration.
Statement from Redbridge Council:
“We were very disappointed to learn that Jerram Falkus — the main contractor responsible for delivering the Wanstead Leisure Centre and school redevelopment project — has entered administration, especially as we were nearing completion.
“Although this setback is entirely beyond our control, the Council remains absolutely committed to completing the new leisure centre that will benefit generations to come, alongside modern classrooms that will give local students the opportunities and learning environment they deserve.
“The Council has now taken formal possession of the site from the Administrator. Additional security personnel have been deployed to ensure the site remains protected, safe and secure. We are also working closely with Wanstead High School to ensure they are fully informed and supported throughout this process.
“We want to reassure parents, staff and the wider community that our commitment to this project has not changed. Work to appoint a new contractor has begun so the final stage of the project can move forward with minimal disruption.
“We recognise that parents, staff and the community will have understandable concerns, and we will continue to provide updates as soon as further information becomes available.”